Inspection
Inspection Details
Equipment ID
13468
13468
Inspection Date
7/2/2025
7/2/2025
Inspection Type
Annual Inspection
Annual Inspection
Inspector Name
Thomas McGrath
Thomas McGrath
Mechanic Name
Jeff Setchfield
Jeff Setchfield
Relief Valve Pressure
NA
NA
Slide
NA
NA
Governor Rope Pull
NA/NA
NA/NA
Door Closing Force
Front 15. Rear 22
Front 15. Rear 22
External ID
bda0dfc0-cb25-4cf8-9e8d-d3fc00495601
bda0dfc0-cb25-4cf8-9e8d-d3fc00495601
Location
Hanley Cooperation Tower
101 S Hanley Rd, Clayton, MO
Phone: (314) 655-5874
Email: JScott@lpc.com
101 S Hanley Rd, Clayton, MO
Phone: (314) 655-5874
Email: JScott@lpc.com
Owner
Attn: James Scott | Property Manager
Hanley Corporate Tower
101 S Hanley Rd, Ste 400, Clayton, MO 63105
Phone: (314) 269-1863
Email: JScott@lpc.com
Hanley Corporate Tower
101 S Hanley Rd, Ste 400, Clayton, MO 63105
Phone: (314) 269-1863
Email: JScott@lpc.com
Billing
Same as Owner
Violations
Code | Item | Section | Reinspection | Red Tag | Reason For Violation | Fixed Date |
---|---|---|---|---|---|---|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators | 2.41 - Maintenance Records | 8.6.1.4 | Testing procedures not in machine room. | 10/16/2019 | ||
MO Minimum : Elevators | (G) - Maintenance, Repair and Replacements | 8.6.1.4 Maintenance records | Need maintenance control program on site posted on controller | 2/12/2021 | ||
MO Minimum : Elevators | (L) - Wire Ropes-Hoisting, Governor and Tiller | (L)1(A) | Rope shackle is rubbing on counterweight frame causing c/w frame to start thinning, this is the same violation found on last years inspection, need a permenant fix to the problem | 2/12/2021 | ||
MO Minimum : Elevators | (G) - Maintenance, Repair and Replacements | 8.6.3.1 Replacement Parts | Rope gripper pads need to be replaced. | 9/17/2021 | ||
MO Minimum : Elevators | (G) - Maintenance, Repair and Replacements | 8.6.1.4.1(a) On-Site Maintenance Records (MCP Records) | Need to include testing procedures in MCP on or before January 1,2022 | 9/17/2021 | ||
MO Minimum : Elevators | (S) - Fire Service | 8.6.11.1 Monthly Test and Log | Perform monthly fire service testing and document on log in machine room | 10/23/2024 | ||
MO Minimum : Elevators | (G) - Maintenance, Repair and Replacements | 8.6.1.2.2(b) On-Site Documentation (Procedures for Inspections and Tests) | Provide testing procedures in the maintenance control program | 10/23/2024 | ||
MO Minimum : Elevators | (G) - Maintenance, Repair and Replacements | (G)1 - 8.6.4.15 Car Emg Sys (Phone or alarm not functioning Mandatory Re-Inspection due in 14 days) | x | Repair phone in car | 7/21/2022 | |
MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (3) Testing Procedures (Re-Inspect) | x | complete annul test within 14 days unintended motion, alternate fire floor | 7/21/2022 | |
MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (3) Testing Procedures (Re-Inspect) | x | Make repairs & reschedule for a complete 5 yr full load test within 30 days | 4/11/2024 | |
A17.1-2016 : Elevators | 2.29 - Car and counterweight safeties | 8.6.4.20.1 | x | x | Adjust counterweight governor for proper setting | 5/6/2024 |
MO Minimum : Elevators | (G) - Maintenance, Repair and Replacements | (G)1 - Car Emergency Systems - 8.6.4.15 (bell, phone & Emergency lighting) | x | x | Repair phone in car emergency light and bell in the car | 5/6/2024 |
MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (3) Testing Procedures (Re-Inspect) | x | Complete 5 year test | 5/6/2024 | |
MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (3) Testing Procedures (Re-Inspect) | x | Test emergency generator | 11/4/2024 | |
A17.1-2016 : Elevators | 1.17 - Standby power operation | 8.6.4.19.7 (Re-Inspection) | x | Test emergency generator | 2/8/2025 |