Inspection
Inspection Details
Equipment ID
27115
27115
Inspection Date
1/29/2026
1/29/2026
Inspection Type
Reinspection
Reinspection
Inspector Name
Cynthia "CJ" Brady
Cynthia "CJ" Brady
Mechanic Name
Tim Switzer
Tim Switzer
Relief Valve Pressure
NA
NA
Slide
NA
NA
Governor Rope Pull
NA
NA
Door Closing Force
NA
NA
External ID
a4a955b6-7a51-4c84-9254-4e5a2fa3183b
a4a955b6-7a51-4c84-9254-4e5a2fa3183b
Location
WITTE BROS TRUCKING
575 WITTE INDUSTRIAL COURT, Troy, MO
Phone: (314) 574-5186
Email: BART@BARTDESIGNBUILD.COM
575 WITTE INDUSTRIAL COURT, Troy, MO
Phone: (314) 574-5186
Email: BART@BARTDESIGNBUILD.COM
Owner
Attn: WITTE BROS TRUCKING
WITTE BROS TRUCKING
575 WITTE INDUSTRIAL COURT, Troy, MO 63379
Phone: (314) 574-5186
Email: BART@BARTDESIGNBUILD.COM
WITTE BROS TRUCKING
575 WITTE INDUSTRIAL COURT, Troy, MO 63379
Phone: (314) 574-5186
Email: BART@BARTDESIGNBUILD.COM
Billing
Same as Owner
Violations
| Code | Item | Section | Reinspection | Red Tag | Reason For Violation | Fixed Date |
|---|---|---|---|---|---|---|
| A17.1-2016 : Elevators | 1.17 - Standby power operation | 8.10.2.2.1(q) | x | Test elevator on generator power. (Building generator powers entire building as if utility power) | 3/5/2026 | |
| A17.1-2016 : Elevators | 1.17 - Standby power operation | 8.10.2.2.1(q) | x | "Elevator Emergency Power" jewel required at main landing. | 3/5/2026 | |
| A17.1-2016 : Elevators | 2.3 - Lighting and receptacles | 2.8.2 | x | Machine space shall have GFCI outlet. Currently standard outlet. | 3/5/2026 | |
| A17.1-2016 : Elevators | 2.11 - Disconnecting Means and Control | 8.7.2.27.4 | x | Mainline disconnect needs location signage (ie: "Elevator mainline/shunt located above"). | 3/5/2026 | |
| A17.1-2016 : Elevators | 2.11 - Disconnecting Means and Control | 8.10.2.2.2(r) | x | Test mainline AUX contacts/shunt operation. | 3/5/2026 | |
| A17.1-2016 : Elevators | 2.14 - Code data plate | 8.7.1.8 | x | Code year data tag shall be installed on controller. | 3/5/2026 | |
| A17.1-2016 : Elevators | 3.10 - Hoistway construction | 8.7.2.1.1 Hoistway Enclosure Walls | x | Fill hoistway fire penetrations with approved material. | 3/5/2026 | |
| A17.1-2016 : Elevators | 3.13 - Windows, projections, recesses, and setbacks | 8.10.2.2.3(s) | x | Top floor door header to hoistway wall space shall equal less than 4" ledge. | 3/5/2026 | |
| A17.1-2016 : Elevators | 3.14 - Hoistway clearances | 8.10.2.2.3(t) | x | Fascia needed between 1st floor header and 2nd floor sill. | 3/5/2026 | |
| A17.1-2016 : Elevators | 5.1 - Pit access, lighting, stop switch, and condition | 8.10.2.2.5(a) | x | Pit sump pump controller is mounted in pit. Relocate to outside of pit/hoistway. | 3/5/2026 | |
| A17.1-2016 : Elevators | 5.1 - Pit access, lighting, stop switch, and condition | 2.2.2.6 Sump Pump Covers | x | Pit sump cover is of solid & sealed construction, preventing water from entering sump. | 3/5/2026 | |
| MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (1) Minimum Standard | x | FAID: need to test all devices connected to elevator. Smokes, heats, shunts. | 3/5/2026 | |
| MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (1) Minimum Standard | x | FAID: 2nd floor lobby heat detector is greater than 24" from it's sprinkler. | 3/5/2026 | |
| A17.1-2016 : Elevators | 1.16 - Rated load, platform area, and data plate | 8.10.2.2.1(p) | x | Install missing "Do not use elevator in case of fire" signage, both floors. | 3/5/2026 | |
| MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (1) Minimum Standard | x | Hoistway mounted horizontal sprinkler "branch lines" are only allowed to supply sprinkler at that single floor level. Top of hoistway branch line can only feed top of hoistway sprinkler. Vertical "risers" shall be located outside of the hoistway (ie: pit sprinkler shall be supplied by 1st floor riser piping). | 3/5/2026 |