Inspection
Inspection Details
Equipment ID
6056
6056
Inspection Date
4/8/2019
4/8/2019
Inspection Type
Reinspection
Reinspection
Inspector Name
Herbert Neulist
Herbert Neulist
Mechanic Name
Relief Valve Pressure
Slide
NA
NA
Governor Rope Pull
NA
NA
Door Closing Force
NA
NA
External ID
0b7a5205-2da7-4b56-9835-1f4a7f1ca0d1
0b7a5205-2da7-4b56-9835-1f4a7f1ca0d1
Location
The 900 Walnut Building
900 WALNUT ST, SAINT LOUIS, MO
900 WALNUT ST, SAINT LOUIS, MO
Owner
Netrality Properties
210 N TUCKER BLVD STE 1030, SAINT LOUIS, MO 63101-1941
210 N TUCKER BLVD STE 1030, SAINT LOUIS, MO 63101-1941
Billing
Attn: 900 Walnut Owner LLC
210 N TUCKER BLVD STE 1030, SAINT LOUIS, MO 63101-1941
210 N TUCKER BLVD STE 1030, SAINT LOUIS, MO 63101-1941
Violations
Code | Item | Section | Reinspection | Red Tag | Reason For Violation | Fixed Date |
---|---|---|---|---|---|---|
MO Minimum : Elevators | (G) - Maintenance, Repair and Replacements | (G)1 Maintenance, Repair and Replacements | 1.6 - The elevator ADA telephone inside the elevator is not working properly. Check and repair the phone line of this phone for proper operation and passenger safety. | 5/20/2019 | ||
A17.1-2016 : Elevators | 4.1 - Car platform guard | 2.15.9 | x | Obstruction in pit will not accommodate a 48" platform guard. Customer will need to request a variance. | 5/31/2023 | |
A17.1-2016 : Elevators | 6.4 - Firefighters' service (A17.1b-1989 and later editions) | 2.27.3.1.1 Phase I Emergency Recall Operation | x | x | Test fire service switch at lobby hall station after new one is installed. | 5/31/2023 |
A17.1-2016 : Elevators | 2.1 - Access to machine space | 2.7.3.4 | x | Provide a self-closing and self-locking machine room door. | 5/31/2023 | |
A17.1-2016 : Elevators | 2.1 - Access to machine space | 2.7.3.1 | x | Provide a permanent step at the machine room entrance. | 5/31/2023 | |
A17.1-2016 : Elevators | 1.17 - Standby power operation | 8.6.4.19.7 (Re-Inspection) | x | Test standby power when installation is complete. | 5/31/2023 | |
A17.1-2016 : Elevators | 3.12 - Pipes, wiring, and ducts | 2.8 | x | Install hoistway duct covers. | 5/31/2023 | |
A17.1-2016 : Elevators | 3.12 - Pipes, wiring, and ducts | 2.8 | x | Remove temporary wiring from hoistway. | 5/31/2023 | |
A17.1-2016 : Elevators | 4.2 - Hoistway doors | 2.11 | x | Cover old escutcheon holes in hoistway doors. | 5/31/2023 | |
A17.1-2016 : Elevators | 2.8 - Pipes, wiring, and ducts | 2.8 | x | Install machine room duct covers. | 5/31/2023 | |
A17.1-2016 : Elevators | 2.8 - Pipes, wiring, and ducts | 2.8 | x | Remove all temporary wiring from the machine room. | 5/31/2023 | |
A17.1-2016 : Elevators | 2.14 - Code data plate | 8.9 | x | 8.10.1.1.4 - Provide acceptance test tag permanently attached to controller. | 5/31/2023 | |
A17.1-2016 : Elevators | 1.17 - Standby power operation | 2.27.2 | x | elevator is on emergency generator power and has not been tested. Generator testing shall occur to complete the annual inspection |