Code Item Section Reinspection Red Tag Reason For Violation Fixed Date
A17.1-2016 : Elevators 5.1 - Pit access, lighting, stop switch, and condition 2.2.2.5 Sump Pump Required/Capacity (Re-Inspect) x Verify the discharge capacity of the sump pump. 7/13/2023
A17.1-2016 : Elevators 3.10 - Hoistway construction 2.1 Seal the joint between the hoistway block walls and the building brick walls.
A17.1-2016 : Elevators 3.10 - Hoistway construction 2.1 Seal all penetrations in the hoistway and machine room.
A17.1-2016 : Elevators 2.10 - Numbering of Elevators, Machines, Controllers, and Disconnect Switches 2.29.1 Install the elevator number on the main floor door jamb.
A17.1-2016 : Elevators 1.15 - sign and operating device symbols 2.26.12 Install a star on the main floor door jamb.
A17.1-2016 : Elevators 2.14 - Code data plate 8.6.1.5 A code data plate is required.
A17.1-2016 : Elevators 1.9 - Power closing of doors or gates 2.13.4.2.2 Complete the door time labels.
A17.1-2016 : Elevators 1.7 - Car door or gate 3.11 Adjust the gap on the front cab door to not exceed 3/8".
A17.1-2016 : Elevators 2.6 - Ventilation 2.7.9.2 Install an A/C system in the machine room.
A17.1-2016 : Elevators 2.1 - Access to machine space 2.7.3.1 A permanent and unobstructed means of access to the elevator machine room shall be provided. Note: During the test, the machine room door was partially blocked. This door shall not be blocked.
A17.1-2016 : Elevators 2.1 - Access to machine space 2.7.3.4 The machine room shall have a self-closing and self-locking door and shall be operable from the interior space without the use of a key.
A17.1-2016 : Elevators 1.6 - Car emergency signal 3.27 (Hydro) Phone or alarm not functioning (Mandatory Re-Inspection due in 14 days) x The in car telephone shall be operational. Note: The phone was tested 5 times. Each time it dialed out but wasn't answered. 10/17/2024
A17.1-2016 : Elevators CSR 40-5.100 State Operating Certificate 5.100(2) Display of Operating Certificate A current MO State operating certificate shall be posted in the elevator equipment room, in a noncombustible frame with a clear protective vision plate over it.
A17.1-2016 : Elevators 2.7 - Fire Extinguisher 8.6.1.6.5 An ABC fire extinguisher with a current test tag shall be mounted in the machine room located convenient to the access door.
A17.1-2016 : Elevators 1.17 - Standby power operation 3.26.10 x The auxiliary power lowering operation shall be functional. 10/17/2024
conversion conversion n/a 4"x 4" electrical junction box in machine room is missing its cover. Said junction box shall have a cover installed. 9/4/2019
MO Minimum : Elevators (B) - Car Enclosure: Passenger (B)11 Phone or alarm not functioning ( Mandatory Re-Inspection due in 14 days) x In cab emergency telephone shall work. 9/21/2018
MO Minimum : Elevators (B) - Car Enclosure: Passenger (B)11 Phone or alarm not functioning ( Mandatory Re-Inspection due in 14 days) x The in car emergency telephone shall be operational. 7/22/2019
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements 8.6.1.4 Maintenance records A code compliant MCP and all the on-site documentation required by A17.1 2016 - 8.6.1.2.2 and 8.6.1.4 shall be provided in the machine room. (This item is for notification purposes for future violation in 2022) 1/4/2024
MO Minimum : Elevators 11 CSR 40-5.090 Inspection and Testing 8.6.5.16.5 Over Speed Valve Testing This elevator is equipped with an over speed valve that in not sealed. A category 5 test shall be performed on the over speed valve in 2021 or 2022. The valve shall be sealed and tagged after the category 5 test. 8/26/2022
MO Minimum : Elevators (A) - Hoistways (A)16 NEC - The sump pump shall have a maximum cord length of 6 feet.
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements 8.6.1.6.7 Signs and Data Plates An acceptance test tag is required.
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements (G)1 - 8.6.4.15 Car Emg Sys (Phone or alarm not functioning Mandatory Re-Inspection due in 14 days) x The in car emergency telephone shall be operational. 1/19/2024