ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
CSR 40-5.100 State Operating Certificate
|
5.100(2) Display of Operating Certificate
|
|
|
A current MO state operating certificate shall be displayed in the elevator machine room.
|
2/13/2024
|
MO Minimum : Elevators
|
CSR 40-5.100 State Operating Certificate
|
5.100(2) Display of Operating Certificate
|
|
|
A current MO State operating certificate shall be posted in the elevator equipment room, in a noncombustible frame with a clear protective vision plate over it.
|
2/13/2024
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.36 - Hydraulic Cylinders
|
8.6.5.5.1 Examination and Maintenance of Packing Glands and Seals
|
x
|
|
During the relief valve test, the packing on one of the jacks failed. Replace packing and re-test. Unit shut down for repairs.
|
11/1/2021
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.11 - Disconnecting Means and Control
|
2.26.4
|
|
|
Feeder locations for the main and lighting branch circuits shall be marked on the disconnects.
|
2/13/2024
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
CSR 40-5.100 State Operating Certificate
|
5.100(2) Display of Operating Certificate
|
|
|
Post the current state operating certificate in the elevator machine room.
|
2/13/2024
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.41 - Maintenance Records
|
8.6.1.4
|
|
|
Provide code compliant MCP. Documents on site not complete.
|
2/13/2024
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
8.11 Periodic Inspection and Test.
|
x
|
|
The inspection is incomplete. The following items still need to be tested: Door pressure, fire service, emergency light, emergency bell, and emergency phone.
|
11/1/2021
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
8.6.5.16.5 Over Speed Valve Testing
|
|
|
This elevator is equipped with an over speed valve. A category 5 test shall be performed on the over speed valve in 2021 or 2022. The valve shall be sealed and tagged after the category 5 test.
|
2/13/2024
|