A17.1-2016 : Elevators
|
5.15.2 Unsealed Overspeed Valve
|
8.6.5.16.5 (Re-Inspect)
|
x
|
|
OSV in the pit is unsealed, provide testing.
|
12/4/2024
|
MO Minimum : Elevators
|
CSR 40-5.100 State Operating Certificate
|
5.100(2) Display of Operating Certificate
|
|
|
Post current State Elevator Certificate.
|
|
MO Minimum : Elevators
|
CSR 40-5.100 State Operating Certificate
|
5.100(2) Display of Operating Certificate
|
|
|
Post current State Elevator Certificate.
|
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
8.6.5.16.5 Over Speed Valve Testing (Re-Inspect)
|
x
|
|
This elevator has an overspeed valve device installed that is not sealed and is now required to have a 5 year full load test performed. This requirement is due to the State of Missouri adopting the A17.1 2016 version of the elevator safety code.
|
10/20/2023
|