MO Minimum : Elevators
|
(F) - Electrical Switches
|
(F)9
|
|
|
Sprinkler heads have been added to the elevator machine room without the required heat detectors to activate the shunt trip disconnect before the application of water. Heat detectors shall be installed within 2’ of each sprinkler head to activate the shunt trip disconnect.
|
7/10/2020
|
MO Minimum : Elevators
|
(F) - Electrical Switches
|
(F)9
|
|
|
Sprinkler heads have been added to the elevator machine room without the required heat detectors to activate the shunt trip disconnect before the application of water. Heat detectors shall be installed within 2’ of each sprinkler head to activate the shunt trip disconnect.
|
7/10/2020
|
MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
8.6.1.6 General Maintenance Methods
|
|
|
The ventilation fan in the controller shall be repaired to provide proper operation temperature for the elevator controller with the controller doors fully closed as designed. At this time controller doors have been removed from the controller allowing exposed wiring to be accessible to damage.
|
12/9/2020
|
MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
8.6.4.11 Runby (Re-Inspection)
|
x
|
|
The counterweight is touching the oil buffer when the elevator travels to the top floor. The hoist ropes shall be shortened to provide a minimum runby of 6 inches.
|
12/17/2020
|
MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
(G)1 Maintenance, Repair and Replacements
|
|
|
The ventilation fan in the controller shall be repaired to provide proper operation temperature for the elevator controller with the controller doors fully closed as designed. At this time controller doors have been removed from the controller allowing exposed wiring to be accessible to damage.
|
7/10/2020
|
MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
(G)1 Maintenance, Repair and Replacements
|
|
|
The “Elevator Inspection” operation does not work in the elevator controller. Repair operation to work as designed.
|
7/10/2020
|
A17.1-2016 : Elevators
|
1.17 - Standby power operation
|
8.6.4.19.7 (Re-Inspection)
|
x
|
|
Standby power needs to be tested. Re-inspection required
|
11/15/2023
|
A17.1-2016 : Elevators
|
1.20 - Earthquake Inspection and Tests (Seismic Risk Zone 2 or Greater)
|
8.11.2.1.1(y)
|
x
|
|
8.6.4.19.17 The earthquake operation failed to operate when activated. Repair the activation devices to operate and perform for passenger safety.
|
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
x
|
|
The testing has not been completed on the elevator at this time. The fireman’s service testing shall be performed before the inspection is completed.
|
|
conversion
|
conversion
|
n/a
|
|
|
The ventilation fan in the controller shall be repaired to provide proper operation temperature for the elevator controller with the controller doors fully closed as designed.
|
7/10/2020
|
conversion
|
conversion
|
n/a
|
|
|
The machine room lighting has been changed to a motion type switch to activate. While this is an energy saving measure, it also is a safety/code concern. Without motion, the switch deactivates the lighting, thereby leaving maintenance personnel with no lighting. Remove motion type switch to a conventional on/off switch.
|
7/10/2020
|