MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
8.11.1.4(a) Elevators Placed in Inactive Status
|
x
|
x
|
Attempted an inspection to put elevator into inactive status. Could not land car on the buffers. Fuses must be removed as well. Re-Inspection required to allow unit to be placed into inactive status.
|
10/10/2023
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
CSR 40-5.100 State Operating Certificate
|
5.100(2) Display of Operating Certificate
|
|
|
Display a current state operating certificate in the machine room.
|
3/20/2022
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
8.11.1.4(a) Elevators Placed in Inactive Status
|
x
|
x
|
This elevator has been placed into inactive status, effective for 2 years. The conditions required by A17.1-2016, 8.11.1.4(a) have been met. Elevator is positioned at rest at the bottom of the hoistway, doors are closed and locked, fuses removed, and elevator red tagged and locked out.
|
|