Code | Item | Section | Reinspection | Red Tag | Reason For Violation | Fixed Date |
---|---|---|---|---|---|---|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators | 1.17 - Standby power operation | 8.11.2.2.7 | x | Elevators connected to a standby or emergency generator shall be tested for operation on standby or emergency power. Re-inspection required | 1/21/2023 | |
MO Minimum : Elevators | 11 CSR 40-5.090 Inspection and Testing | (3) Testing Procedures (Re-Inspect) | x | Category 5 full load test is incomplete, need to perform the following tests: Traction machine brake with 125% of rated load, unintended car movement with 125% of rated load, car safeties at rated speed with rated load, car buffer at rated speed with rated load & counterweight buffer at rated speed with no load. Re-inspection required | 9/21/2024 |