MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
(G)1 - 8.6.4.13 - Door systems
|
x
|
|
Replace missing hoistway door gibb at 2nd floor landing. Re-inspection required
|
|
A17.1-2016 : Elevators
|
1.17 - Standby power operation
|
8.6.4.19.7 (Re-Inspection)
|
x
|
|
Auxiliary battery lowering device (emergency recue unit) does not work, needs repaired. Re-inspection required
|
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
x
|
|
Need to perform relief valve system pressure test. Re-inspection required
|
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.37 - Pressure Switch
|
3.26.8 Pressure Switch
|
x
|
|
The low pressure switch shall be operational.
|
7/20/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
5.1 - Pit access, lighting, stop switch, and condition
|
2.2.2.6 Sump Pump Covers
|
|
|
The pit sump pump hole shall have a cover installed.
|
2/1/2021
|
conversion
|
conversion
|
n/a
|
|
|
The fire extinguisher in the machine room is expired.
|
2/1/2021
|
conversion
|
conversion
|
n/a
|
|
|
Remove all non-elevator related equipment from the elevator machine room.
|
2/1/2021
|
conversion
|
conversion
|
n/a
|
|
|
Sump hole in the pit shall be covered.
|
2/1/2021
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.37 - Pressure Switch
|
3.26.8 Pressure Switch
|
|
|
Pressure switch inoperable
|
1/19/2023
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.37 - Pressure Switch
|
3.26.8 Pressure Switch
|
x
|
|
Pressure switch inoperable. Re-inspection required
|
1/19/2023
|