ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
4.2 - Hoistway doors
|
8.6.4.13
|
|
|
Hoistway door bottom retainers required
|
7/19/2022
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.8 - Pipes, wiring, and ducts
|
8.11.2.1.2(h)
|
|
|
Install wiring cover on hoist machine. Violation code 2.8.1
|
7/19/2022
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
x
|
|
Testing incomplete, need to test Emergency power. Re-inspection required
|
1/9/2024
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
6.4 - Firefighters' service (A17.1b-1989 and later editions)
|
2.27.2-2.27.8
|
x
|
x
|
Fire service operation, smokes, heats, powered hoistway venting, and other associated items must be completed and tested.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
1.6 - Car emergency signal
|
8.11.2.1.1(f) (Insp code) Phone or alarm not functioning (Mandatory Re-Inspection due in 14 days)
|
x
|
|
The in car emergency telephone shall be operational.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
1.5 - Car lighting and receptacles
|
2.14.7.1.3 Provide Auxiliary Lighting
|
x
|
|
The emergency lighting shall be operational.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
1.6 - Car emergency signal
|
8.11.2.1.1(f) (Insp code) Phone or alarm not functioning (Mandatory Re-Inspection due in 14 days)
|
x
|
|
The alarm bell shall operate on auxiliary power.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
1.4 - Sills and car floor
|
8.11.2.1.1(d)
|
x
|
|
The elevator floor and lobby floors must be finished and landings sills grouted.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.11 - Disconnecting Means and Control
|
2.26.4
|
x
|
|
Permanent main line and lighting power shall be provided and shall have feeder locations marked.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.10 - Hoistway construction
|
2.1
|
x
|
|
The penetrations in the hoistway shall be sealed with approved solid material.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.41 - Maintenance Records
|
8.6.1.4
|
x
|
|
A written maintenance control program (MCP) shall be in place to maintain the equipment in compliance with the requirements of Section 8.6.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.12 - Pipes, wiring, and ducts
|
2.8
|
x
|
|
All electrical device and wireway covers shall be installed.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.12 - Pipes, wiring, and ducts
|
2.8
|
x
|
|
A light switch, lighting, and GFCI receptacle must be installed in the overhead.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
5.1 - Pit access, lighting, stop switch, and condition
|
2.8
|
x
|
|
A light switch, light, and GFCI receptacle must be installed in the pit.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.7 - Fire Extinguisher
|
8.6.1.6.5
|
x
|
|
A fire extinguisher must be provided and mounted convenient to the top landing hall door.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
5.1 - Pit access, lighting, stop switch, and condition
|
2.2.2.5 Sump pump shall be provided
|
x
|
|
Installation of the pit sump pump must be completed and the cover must be installed.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
6.4 - Firefighters' service (A17.1b-1989 and later editions)
|
2.27.2-2.27.8
|
x
|
x
|
The building fire control station must be installed and tested.
|
7/31/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.42 Seismic (Earthquake protection)
|
8.4.10
|
x
|
|
The counterweight displacement system must be installed and tested.
|
7/31/2020
|