A17.1-2016 : Elevators
|
1.17 - Standby power operation
|
8.6.4.19.7 (Re-Inspection)
|
x
|
|
Emergency power generator to be tested when lobby panel is completed, providing selector switch
|
8/12/2024
|
A17.1-2016 : Elevators
|
3.10 - Hoistway construction
|
8.7.2.1.1 Hoistway Enclosure Walls
|
x
|
|
3.10 Hoistway construction - 3.1 - Seal all hoistway penetrations and non factory seams in core board.
|
8/12/2024
|
A17.1-2016 : Elevators
|
3.13 - Windows, projections, recesses, and setbacks
|
2.1.5
|
x
|
|
All beveled surfaces shall be 70 degree bevel and capable of withstanding a 100# per soft load at aright angle
|
8/12/2024
|
A17.1-2016 : Elevators
|
6.4 - Firefighters' service (A17.1b-1989 and later editions)
|
3.27
|
x
|
x
|
Due to the addition of sprinkler heads in the elevator pit a smoke detector shall be installed in the elevator pit and recall tested.
|
8/26/2024
|
A17.1-2016 : Elevators
|
2.11 - Disconnecting Means and Control
|
3.26.1
|
|
|
Due to the addition of sprinkler heads in the elevator machine room a heat detector is required within 24 inches of every head in the machine room to activate the shunt trip and tested
|
10/11/2024
|