Code Item Section Reinspection Red Tag Reason For Violation Fixed Date
A17.1-2016 : Elevators 2.11 - Disconnecting Means and Control 3.26.1 No No 2.11 Due to the addition of sprinkler heads in the elevator machine room a heat detector is required within 24 inches of every head in the machine room to activate the shunt trip and tested 10/11/2024
A17.1-2016 : Elevators 2.1 - Access to machine space 2.7.1.1 No No All penetrations in the machine room shall be sealed to maintain the fire-resistive construction.
A17.1-2016 : Elevators 6.4 - Firefighters' service (A17.1b-1989 and later editions) 3.27 Yes Yes Due to the addition of sprinkler heads in the elevator pit a smoke detector shall be installed in the elevator pit and recall tested. 8/26/2024
A17.1-2016 : Elevators 3.10 - Hoistway construction 3.1 Yes No Seal hoistway penetrations and non factory seams in shaft liner 8/12/2024
A17.1-2016 : Elevators 1.17 - Standby power operation 3.26.10 Yes No The auxiliary lowering system has not been permanently completed. This system shall be made operational and a reinspection is required.
A17.1-2016 : Elevators 5.1 - Pit access, lighting, stop switch, and condition 2.2.5 No No The elevator pit light did not work on the day of inspection, repair for proper illumination of the pit floor.
A17.1-2016 : Elevators 1.17 - Standby power operation 2.27.2 Yes No The emergency power operation has not been permanently completed. The elevator is on a temporary generator system that does not allow all elevators to operate as designed. The permanent generator system shall be completed and the operation shall conform to this section. Reinspection is required.
MO Minimum : Elevators 11 CSR 40-5.090 Inspection and Testing (3) Testing Procedures (Re-Inspect) Yes No Emergency power testing needs to be performed. Re-inspection required 4/9/2026