Code Item Section Reinspection Red Tag Reason For Violation Fixed Date
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements (G)1 - Door Systems 8.6.4.13 (Re-Inspection) x both of the photo eyes on the rear opening were not working, repair or replace the photo eye 6/14/2023
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements (G)1- 8.6.4.15 Car Emergency Systems (Emergency Light) (Re-Inspection) x Emergency lights did not come on, alarm bell did work, repair light fixture for emergency lights 8/30/2024
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements 8.6.1.4.1(a) On-Site Maintenance Records (MCP Records) Maintenance Control Program documents are missing
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements (G)1 - 8.6.4.13 - Door systems Mechanical safety edge is functional but the light ray is not on the rear entrance
MO Minimum : Elevators (H) - Machine Rooms (H)2 Pipes conveying liquid, gas, or vapor that cross overhead of elevator equipment or come in close proximity of the equipment shall be guarded or guttered.
MO Minimum : Elevators CSR 40-5.100 State Operating Certificate 5.100(2) Display of Operating Certificate Post current copy of the state operating certificate in the machine room
MO Minimum : Elevators (S) - Fire Service 8.6.11.1 Monthly Test and Log Post monthly fire service test log in the machine room
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements 8.6.1.4 Maintenance records Provide complete MCP in the machine room according to 8.6
MO Minimum : Elevators CSR 40-5.100 State Operating Certificate 5.100(2) Display of Operating Certificate The building shall post the operating certificate in the elevator equipment room, and it needs to be updated with a new copy annually.
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements (G)1 - Door Systems 8.6.4.13 (Re-Inspection) x The rear entrance light ray is not working, the mechanical edge is working 8/30/2024
MO Minimum : Elevators (I) - Pits (I)1 there was water in the pit on the day of the inspection, maintain a dry pit