Code Item Section Reinspection Red Tag Reason For Violation Fixed Date
A17.1-2016 : Elevators 3.11 - Hoistway smoke control 2.1.4 x Fire doors and magnets need to be installed on frames at landings and tested for proper operation. 8/15/2025
A17.1-2016 : Elevators 3.12 - Pipes, wiring, and ducts 2.8 x Sump pump discharge pipe must be non-combustible. 8/15/2025
A17.1-2016 : Elevators 3.12 - Pipes, wiring, and ducts 2.8 x Sump pump control system boxes must be removed from pit or change to a different pump, and oil minder pump is not required since this is not a hydraulic elevator. 8/15/2025
MO Minimum : Elevators 11 CSR 40-5.090 Inspection and Testing (3) Testing Procedures (Re-Inspect) x Provided letter from mechanical contractor stating purpose of louvered vent at top of hoistway and vent in wall of hoistway behind rail at first floor. Letter needed to verify control of smoke and gases, equipment exposed to weather, temperature and humidity control, and machine room venting for MRL unit. 8/15/2025