Code Item Section Reinspection Red Tag Reason For Violation Fixed Date
A17.1-2016 : Elevators 5.1 - Pit access, lighting, stop switch, and condition 8.10.2.2.5(a) Yes No Pit sump pump controller is mounted in pit. Relocate to outside of pit/hoistway. 3/5/2026
A17.1-2016 : Elevators 5.1 - Pit access, lighting, stop switch, and condition 2.2.2.6 Sump Pump Covers Yes No Pit sump cover is of solid & sealed construction, preventing water from entering sump. 3/5/2026
A17.1-2016 : Elevators 3.14 - Hoistway clearances 8.10.2.2.3(t) Yes No Fascia needed between 1st floor header and 2nd floor sill. 3/5/2026
A17.1-2016 : Elevators 3.13 - Windows, projections, recesses, and setbacks 8.10.2.2.3(s) Yes No Top floor door header to hoistway wall space shall equal less than 4" ledge. 3/5/2026
A17.1-2016 : Elevators 3.10 - Hoistway construction 8.7.2.1.1 Hoistway Enclosure Walls Yes No Fill hoistway fire penetrations with approved material. 3/5/2026
A17.1-2016 : Elevators 2.3 - Lighting and receptacles 2.8.2 Yes No Machine space shall have GFCI outlet. Currently standard outlet. 3/5/2026
A17.1-2016 : Elevators 2.14 - Code data plate 8.7.1.8 Yes No Code year data tag shall be installed on controller. 3/5/2026
A17.1-2016 : Elevators 2.11 - Disconnecting Means and Control 8.7.2.27.4 Yes No Mainline disconnect needs location signage (ie: "Elevator mainline/shunt located above"). 3/5/2026
A17.1-2016 : Elevators 2.11 - Disconnecting Means and Control 8.10.2.2.2(r) Yes No Test mainline AUX contacts/shunt operation. 3/5/2026
MO Minimum : Elevators 11 CSR 40-5.090 Inspection and Testing (1) Minimum Standard Yes No FAID: need to test all devices connected to elevator. Smokes, heats, shunts. 3/5/2026
MO Minimum : Elevators 11 CSR 40-5.090 Inspection and Testing (1) Minimum Standard Yes No FAID: 2nd floor lobby heat detector is greater than 24" from it's sprinkler. 3/5/2026
MO Minimum : Elevators 11 CSR 40-5.090 Inspection and Testing (1) Minimum Standard Yes No Hoistway mounted horizontal sprinkler "branch lines" are only allowed to supply sprinkler at that single floor level. Top of hoistway branch line can only feed top of hoistway sprinkler. Vertical "risers" shall be located outside of the hoistway (ie: pit sprinkler shall be supplied by 1st floor riser piping). 3/5/2026
A17.1-2016 : Elevators 1.17 - Standby power operation 8.10.2.2.1(q) Yes No Test elevator on generator power. (Building generator powers entire building as if utility power) 3/5/2026
A17.1-2016 : Elevators 1.17 - Standby power operation 8.10.2.2.1(q) Yes No "Elevator Emergency Power" jewel required at main landing. 3/5/2026
A17.1-2016 : Elevators 1.16 - Rated load, platform area, and data plate 8.10.2.2.1(p) Yes No Install missing "Do not use elevator in case of fire" signage, both floors. 3/5/2026