MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
Yes
|
No
|
All fire service aspects shall be checked when repaired and complete
|
7/14/2026
|
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
Yes
|
No
|
Emergency back up battery system shall be checked when repaired.
|
7/14/2026
|
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
Yes
|
No
|
All governor and safety test shall be done.
|
7/14/2026
|
|
MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
(G)1 Maintenance, Repair and Replacements
|
Yes
|
No
|
All covers and signage shall be installed
|
7/14/2026
|
|
A17.1-2016 : Elevators
|
2.3 - Lighting and receptacles
|
2.7.9.1
|
Yes
|
No
|
Lighting shall not be less than 200lux/19fc at floor in front of controller.
|
7/23/2026
|
|
A17.1-2016 : Elevators
|
2.10 - Numbering of Elevators, Machines, Controllers, and Disconnect Switches
|
8.10.2.2.2(o)
|
Yes
|
No
|
Lighting and Mainline disconnects, in Electrical Closet, shall be labeled with location of feeder breakers, and function
|
7/23/2026
|
|
A17.1-2016 : Elevators
|
2.10 - Numbering of Elevators, Machines, Controllers, and Disconnect Switches
|
8.10.2.2.2(o)
|
Yes
|
No
|
Lighting and Mainline breakers, in 4th Floor Elevator Testing Panel, shall be labeled with location of feeder breakers, and function
|
7/23/2026
|
|
A17.1-2016 : Elevators
|
9.20 - Earthquake Inspection and Tests (Seismic Risk Zone 2 or Greater)
|
8.5
|
Yes
|
No
|
The seismic still needs to be checked.
|
7/14/2026
|
|
A17.1-2016 : Elevators
|
2.40 - Maintenance Records
|
8.6.1.2.2 On-Site Documentation
|
Yes
|
No
|
MCP's shall be left onsite.
|
7/14/2026
|
|
A17.1-2016 : Elevators
|
3.10 - Hoistway construction
|
8.7.2.1.1 Hoistway Enclosure Walls
|
Yes
|
No
|
Fire caulk/fill holes and voids in Hoistway walls, as marked with Orange Paint.
|
7/23/2026
|