Code Item Section Reinspection Red Tag Reason For Violation Fixed Date
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators 1.17 - Standby power operation 8.11.2.1.1(q) x emergency power will be tested at later time when their system is corrected/time set when all 3 mods can be tested 12/3/2019
A17.1-2016 : Elevators 1.17 - Standby power operation 8.7.2.28 x Eleveator faulted out upon transfer from normal to emergency power 2/5/2021
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators 2.2 Headroom 8.11.2.1.2(b) Building concrete beam between pump unit and controller in machine room-clearance 71 1/2"--110.26(A)(3) NEC requires 78"--variance required 6/1/2020
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators 2.2 Headroom 8.11.2.1.2(b) Headroom clearance (71 1/2") beam variance will need to be requested 6/1/2020
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators 2.2 Headroom 8.11.2.1.2(b) x machine room clearances/ concrete structural beam between pump unit & controller measures 71 1/2" required by NEC 78" variance required 12/3/2019
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators 2.3 - Lighting and receptacles 8.11.2.1.2(c) x additional lighting needs to be added to machine room 12/3/2019
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators 6.2 - Operation of elevators under fire and other emergency conditions (A17.1-1981 through A17.1b-1983) 8.11.2.2.6 x x Shunt trip did not work --Reinspect required 12/3/2019