A17.1-2016 : Elevators
|
6.5 -Acceptance Checklist for Firefighters' Service (ASME A17.1-2000 and CSA B44-00): Automatic Elevators
|
2.27.1
|
x
|
|
FEO Phase I and II need to be tested when hall risers are installed.
|
|
|
A17.1-2016 : Elevators
|
1.5 - Car lighting and receptacles
|
2.14.7
|
x
|
|
110 disconnect shall be moved to an accessible location in the Machine Room
|
|
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.41 - Maintenance Records
|
8.6.1.4
|
|
|
Written maintenance control program shall be provided on-site for each elevator.
|
12/19/2022
|
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
5.2 - Bottom clearance, runby, and minimum refuge space
|
8.11.2.1.5(b)
|
x
|
|
Counterweight buffer is being compressed 2" when car is at a top landing. Shorten suspension ropes to maintain proper counterweight runby.
|
2/18/2022
|