MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
8.6.1.2.2 On-Site Documentation
|
|
|
A code compliant MCP and all the on-site documentation required shall be provided in the machine room.
|
10/22/2025
|
|
MO Minimum : Elevators
|
(S) - Fire Service
|
8.11.2.2.6 Firefighters’ Emergency Operation (Re-Inspection)
|
x
|
|
Fire service call cancel button shall work. 14 days to be corrected and re-inspected or unit to be red tagged.
|
10/22/2025
|
|
MO Minimum : Elevators
|
(S) - Fire Service
|
211.8 Switch Keys
|
x
|
|
Fire service phase 2 key switch shall have only 2 positions. Unit does not have "HOLD". Bezel is correct with only "OFF" and "ON".
|
10/22/2025
|
|
A17.1-2016 : Elevators
|
2.40 - Maintenance Records
|
8.6.1.2.2 On-Site Documentation
|
|
|
Need a maintenance control program on site
|
10/22/2025
|
|
A17.1-2016 : Elevators
|
5.15 - Overspeed Valve
|
8.6.5.16.5
|
x
|
|
Overspeed valve testing is past due. Tessting to be completed in 30 days are less otherwise unit will be red tagged out of service
|
7/10/2025
|
|
MO Minimum : Elevators
|
(G) - Maintenance, Repair and Replacements
|
8.6.1.4 Maintenance records
|
x
|
|
A code compliant MCP and all the on-site documentation required shall be provided in the machine room.
|
|
|
MO Minimum : Elevators
|
(S) - Fire Service
|
8.11.2.2.6 Firefighters’ Emergency Operation (Re-Inspection)
|
x
|
|
Fire service call cancel button shall work. 14 days to be corrected and re-inspected or unit to be red tagged. Violation unable to be checked at time of alteration inspection on 10/16/25 due to unit going down.
|
|
|
MO Minimum : Elevators
|
(S) - Fire Service
|
211.8 Switch Keys
|
x
|
|
Fire service phase 2 key switch shall have only 2 positions. Unit does not have "HOLD". Bezel is correct with only "OFF" and "ON". Violation unable to be checked at time of alteration inspection on 10/16/25 due to unit going down.
|
|
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
x
|
|
This repair/alteration inspection included witnessing working pressure and relief pressure. The working pressure was 340#. While testing for relief pressure, the unit went down. This inspection was not completed. Relief valve pressure shall be successfully tested.
|
|