conversion
|
conversion
|
n/a
|
|
|
Negative counterweight runby, repair.
|
6/27/2018
|
MO Minimum : Elevators
|
(A) - Hoistways
|
(A)16
|
|
|
When sprinkler systems are present in the hoistway, means shall be provided to automatically disconnect the main line power supply to the affected elevator prior to the application of water.
|
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
x
|
|
Incomplete test, Fire service and emergency power shall be tested.
|
5/13/2025
|
MO Minimum : Elevators
|
11 CSR 40-5.090 Inspection and Testing
|
(3) Testing Procedures (Re-Inspect)
|
x
|
|
The emergency generator testing failed. The transfer switch failed to operate properly. Re-inspection required
|
|