Code Item Section Reinspection Red Tag Reason For Violation Fixed Date
MO Minimum : Elevators 11 CSR 40-5.090 Inspection and Testing (3) Testing Procedures (Re-Inspect) x The plunger gripper is due to be tested with a full load this year.
MO Minimum : Elevators (G) - Maintenance, Repair and Replacements (G)1 - 8.6.1.6.3 Controllers ,Wiring and Wiring Diagrams A legible copy of the controller schematics shall be kept in the machine room. 7/22/2020
MO Minimum : Elevators (H) - Machine Rooms (H)9 x Each elevator having polyphase alternating current power supply shall be provided with means to prevent the starting of the elevator motor if: (A) The phase rotation is in the wrong direction; or (B) There is a failure of any phase.
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators CSR 40-5.100 State Operating Certificate 5.100(2) Display of Operating Certificate Display current state operating certificate. 6/12/2019
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators CSR 40-5.100 State Operating Certificate 5.100(2) Display of Operating Certificate Up to date operating certificate required in the machine room. 8/2/2023
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators 2.41 - Maintenance Records 8.6.1.4 A code compliant MCP and all the on-site documentation required by A17.1 2016 - 8.6.1.2.2 and 8.6.1.4 shall be provided in the machine room. (This item is for notification purposes for future violation in 2022) 5/11/2021