ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.10 - Hoistway construction
|
2.1
|
x
|
|
Seal all penetrations in the hoistway.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.10 - Hoistway construction
|
2.1
|
x
|
|
Complete the construction of the top of the hoistway.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
1.16 - Rated load, platform area, and data plate
|
2.16
|
x
|
|
Correct the capacity plate on the COP. Currently says 2500 lbs. and the actual capacity is 2000 lbs.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
6.4 - Firefighters' service (A17.1b-1989 and later editions)
|
2.27.7 Firefighters' Emergency Operation: Operating Procedures
|
x
|
|
Install all fire service signage and do not use in case of fire signage.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.4 - Machine space
|
2.7.1.1
|
x
|
|
Seal all penetrations in the machine room.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.1 - Access to machine space
|
2.7.1.1
|
x
|
|
2.7.1.1.2 - The machine room door shall have a fire rating of 1.5 hours.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.12 - Pipes, wiring, and ducts
|
2.8
|
x
|
|
A sprinkler head shall be installed in the pit.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.12 - Pipes, wiring, and ducts
|
2.8
|
x
|
|
Install all covers on junction boxes and wiring ducts in the hoistway.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
3.12 - Pipes, wiring, and ducts
|
2.8
|
x
|
|
Finish the installation of the sprinkler head at the top of the hoistway.
|
1/3/2020
|
ASME A17.1 2004 with 2005 Addendum and 2005 : Elevators
|
2.8 - Pipes, wiring, and ducts
|
2.8.2 (Re-Inspection)
|
x
|
|
Finish the installation of the sprinkler head in the machine room.
|
1/3/2020
|